The typical scope of works covered by our Installation Field Service Crew includes but is not limited to,
- Site Establishment including Principal Contractor Duties
- Supervision of unloading, placement of anti vibration pads and positioning on center lines
- Inspection and assessment of all delivered components prior to commencement
- Unpacking, inspection and preparation of auxiliary components
- Preparation of all gaskets as/if required
- Assembly/installation of components, bushings, oil pumps, A-frame & radiators, conservator, pipe-work etc.
- Application of vacuum prior to oil filling
- Oil preparation and streamline filtering during fill process
- Assembly and installation of fans and control wiring etc.
- Oil Sampling & Analysis
- PCP has 100kva and 17kva generator sets.
- Transformer Testing includes
– Insulation Resistance, Polarisation Index
– DC Winding Resistance
– Transformer Turns Ratio & Vector
– OTI, WTI calibration/verification
– Functional/operation checks
– CT Polarity, Ratio, Resistance Mag Curve
– Sweep Frequency Response Analysis
– DLA, Transformer, Bushings, Excitation Current C1/C2
– Transformer Impedance
– Aerial Inspection of Transformer/Switchyards (UAV)
– Transformer Steam Cleaning with a three phase diesel steam cleaner.
- PCP has added to its testing ability by purchasing an Omicron DIRANA Test Set. The DIRANA test set is a dielectric response analyser for the insulation diagnoses of high voltage assets in the power industry. DIRANA provides an indication of the insulation condition such as:
- – Moisture content in the oil/paper insulation
- – Condition of OIP, RBP, and RIP high-voltage bushings
- – Condition of the generator, motor and cable insulation
- Complete final inspection and touch-up
- Site tidy and disestablishment
This work is performed in accordance with your specification, health & safety, environmental, procedural and timing requirements.